Spetz Specs No. 5609: step-by-step build guide

Freestanding Wood-Sided Outdoor Shower with Rain Head

The complete step-by-step guide made from Indy Farm Life's YouTube video, free on Spetz. For the video, a step-by-step player and answers to your questions, see the Freestanding Wood-Sided Outdoor Shower with Rain Head project page.

Freestanding Wood-Sided Outdoor Shower with Rain Head

7 steps, 16 parts, 13 tools, 24 materials

Overview

Finished size: 60 in W x 96 in D x 90 in H

What You're Building

Why This Design Works

What It Takes

What Decides Success

Overall dimensions
Overall dimensions

Health and safety

Saws, Nailer, and Impact Driver

Wood Preservative and Treated Lumber

Excavation, Aggregate, and Tractor Work

Ladder Work and Structural Stability

Tools

Materials

Hardware

HardwareSizeCountUsed in steps
Framing and siding nails2, 3, 4, 5, 6, 7
Exterior structural wood screws5
Washered roofing screws6

Cut list

PartNameQtySizeNotes
ACorner postx43 1/2" (T) × 3 1/2" (W) × 144" (H)Set 3 ft deep into post holes; approximately 1.5 ft of additional post height is buried when bringing the base up to grade.
BDoorway partition postx13 1/2" (T) × 3 1/2" (W) × 96" (H)Set into a hole dug against the 2x6 threshold to leave a 30 in doorway opening; fastened to the base framing and upper cross brace with structural screws.
CBase side containment boardx41 1/2" (T) × 5 1/2" (W) × 72" (L)Installed two boards high on the inside of the 4x4 posts along both left and right sides to retain #8 gravel.
DBase crossmemberx21 1/2" (T) × 5 1/2" (W) × 60" (L)Spans across the width of the structure to separate the entryway from the interior shower bay and retain gravel.
EEntryway floor joist and blockingx41 1/2" (T) × 5 1/2" (W) × 24" (L)Framed into a grid across the entryway floor bays outside the shower stall to support the composite decking and retain gravel.
FWall studx81 1/2" (T) × 3 1/2" (W) × 78" (H)Installed vertically between the 4x4 corner posts (2 studs on the rear plumbing wall, 3 on the left side wall, and 3 on the right side wall).
GRear wall horizontal platex21 1/2" (T) × 3 1/2" (W) × 53" (L)Fits horizontally between the rear 4x4 corner posts for the rear plumbing wall framing.
HSide wall top platex21 1/2" (T) × 3 1/2" (W) × 65" (L)Spans horizontally between the front and rear 4x4 corner posts on the left and right walls.
IFront partition and niche framing memberx61 1/2" (T) × 3 1/2" (W) × 23" (L)Horizontal framing and recessed wall niche blocking between the front corner post and the doorway partition post.
JRoof purlinx71 1/2" (T) × 3 1/2" (W) × 60" (L)Spaced 16 in on center across the roof framing to support the corrugated polycarbonate roof panels.
KRear wall rough-sawn siding boardx303/4" (T) × 5 1/2" (W) × 60" (L)Rough-sawn 1x boards of varying widths nailed horizontally from the bottom up without spacers on the rear exterior wall and interior plumbing wall.
LSide wall exterior rough-sawn siding boardx303/4" (T) × 5 1/2" (W) × 72" (L)Rough-sawn 1x boards of varying widths nailed horizontally without spacers across the left and right exterior walls.
MFront partition rough-sawn siding boardx303/4" (T) × 5 1/2" (W) × 30" (L)Nailed horizontally across the exterior and interior faces of the front partition wall and trimmed around the recessed niche.
NInterior side wall car siding boardx283/4" (T) × 5 1/2" (W) × 65" (L)Tongue-and-groove car siding boards installed horizontally across the left and right interior shower stall walls.
OEntryway deck boardx51 1/4" (T) × 6" (W) × 60" (L)Fitted over the 2x6 entryway floor framing; rear board ripped to width and corners notched around the 4x4 posts.
PCorrugated polycarbonate roof panelx31/16" (T) × 20" (W) × 96" (L)Fastened to the seven 2x4 roof purlins with washered roofing screws.

What to buy

Cut diagram
Cut diagram

Before you start

Posts and Sub-Base

Water Supply Setup

Step by step

Step 1: Lay out the drainage pipes

Three pre-wrapped French drain pipes span the sloped base between corner posts.

Watch this step (3:21)

Three wrapped drain pipes in place
Three wrapped drain pipes in place

Parts in this step: (A) Corner post

You'll need: Shovel, Post hole digger, Hand tamper, Pressure-treated posts, #53 limestone gravel, Pre-wrapped drainage pipe, Corrugated drain pipe

  1. 1.1 Set the first pre-wrapped drainage pipe
    • Set the first pre-wrapped drainage pipe between the corner posts (A).
    • Lay the pipe on the sloped #53 limestone base toward the rear drainage ditch.
    • Extend the rear end past back posts to discharge water away from the base.
  2. 1.2 Place the remaining two drainage pipes
    • Set two more pre-wrapped drainage pipes side by side against the first.
    • Span the full interior stall width with the three parallel pipes.
    • Route flexible corrugated drain pipe from the outlets into the drainage ditch.
Step 1, part by part
Step 1, part by part
Four 4x4 corner posts base layout
Four 4x4 corner posts base layout

Key measurements

  • Corner post hole depth: 36 in below grade
  • Post buried in backfill after grading: 18 in additional
  • Shower entrance width: 60 in across front corner posts
  • Tip: Fill ground dips with #53 limestone so the drain pipes keep a steady fall.

Before you move on: Check the limestone bed and three drainage pipes slope continuously to the rear ditch with no belly.

Step 2: Backfill the perimeter and shower base with aggregate

2x6 containment box around the base: backfilled outside with #53 limestone, inside with #8 river rock.

Watch this step (4:26)

Base box filled with river rock
Base box filled with river rock

Parts in this step: (A) Corner post, (C) Base side containment board, (D) Base crossmember

You'll need: Tractor with front-end loader, Shovel, Cordless framing nailer, 2x6 framing lumber, #53 limestone gravel, #8 gravel, Drainage pipe end caps, Hearthstones, Framing and siding nails

  1. 2.1 Dump and shovel #53 limestone around the base perimeter
    • Nail four estimated 72 in base side containment boards (C) two-high inside corner posts (A).
    • Attach two 60 in base crossmembers (D) across front and middle to retain gravel.
    • Dump and shovel #53 limestone gravel outside the 2x6 box.
  2. 2.2 Spread and level the exterior limestone
    • Shovel #53 limestone to bury the exposed exterior corrugated drain pipes.
    • Rake the outer limestone into a smooth ramp meeting the ground.
  3. 2.3 Shovel #8 river rock over the interior drainage pipes
    • Press plastic drainage pipe end caps onto the pre-wrapped pipe ends.
    • Place a loader bucket of clean #8 gravel by the shower frame.
    • Hand-shovel #8 gravel into the shower bay over the three drainage pipes.
  4. 2.4 Level the #8 gravel bed inside the shower bay
    • Fill the inner bay with #8 gravel to the top of lower crossmembers (D).
    • Spread and flatten the river rock with a shovel and your boot.
    • Set nine leftover hearthstones on the level gravel later for solid footing.
Step 2, part by part
Step 2, part by part
2x6 base containment boards on posts
2x6 base containment boards on posts

Key measurements

  • Base side containment board length: 72 in (estimated), stacked two-high per side
  • Base crossmember length: 60 in across shower width
  • Tip: Cap the pre-wrapped pipes before shoveling #8 gravel so loose stones never block the drain channels.
  • Tip: Hand-shovel #8 gravel from the bucket so angled dumping never spills clean stone outside.

Before you move on: Check drainage pipe ends are capped and buried under level #8 river rock.

Step 3: Fill the entryway floor framing with gravel

2x6 entryway floor grid, reinforced with blocking and filled level with #8 gravel.

Watch this step (6:37)

Entryway floor bays filled with gravel
Entryway floor bays filled with gravel

Parts in this step: (D) Base crossmember, (E) Entryway floor joist and blocking

You'll need: Tractor with front-end loader, Shovel, Cordless framing nailer, 2x6 framing lumber, #8 gravel, Framing and siding nails

  1. 3.1 Position the loader bucket over the entryway framing
    • Nail four estimated 24 in entryway floor joists and blocking (E) between front crossmembers (D).
    • Drive the tractor loader bucket of #8 gravel to the front entryway grid.
    • Hold the bucket above the 2x6 framing for easy shoveling.
  2. 3.2 Shovel #8 gravel into the entryway joist bays
    • Shovel #8 gravel from the loader bucket into each entryway grid bay.
    • Spread stone flush with the top of the 2x6 entryway blocking (E).
Step 3, part by part
Step 3, part by part
Entryway floor joist grid
Entryway floor joist grid

Key measurements

  • Entryway joist and blocking length: 24 in (estimated) across the front bay
  • Tip: Add 2x6 entryway blocking before gravel so the composite decking will not flex.

Before you move on: Check the 2x6 entryway frame sits level with gravel flush to the blocking top.

Step 4: Frame the shower walls

Vertical 2x4 studs and horizontal plates frame the rear, left, and right walls between corner posts.

Watch this step (7:04)

Rear and side walls framed
Rear and side walls framed

Parts in this step: (A) Corner post, (F) Wall stud, (G) Rear wall horizontal plate, (H) Side wall top plate

You'll need: Miter saw with stand, Circular saw, Cordless framing nailer, Level, Speed square, Tape measure, Ladder, 2x4 framing lumber, Framing and siding nails

  1. 4.1 Frame the rear plumbing wall with 2x4 studs
    • Cut two 53 in rear wall horizontal plates (G) to fit between rear corner posts (A).
    • Miter-cut two estimated 78 in wall studs (F) for the rear plumbing wall.
    • Plumb the rear plates (G) and studs (F) with a level, then nail.
  2. 4.2 Frame the left side wall
    • Cut one estimated 65 in side wall top plate (H) and three 78 in studs (F).
    • Nail top plate (H) horizontally between the left front and rear corner posts (A).
    • Plumb and nail the three vertical studs (F) evenly across the left wall.
  3. 4.3 Frame the right side wall
    • Cut the second estimated 65 in side wall top plate (H) and three 78 in studs (F).
    • Check corners with a speed square; adjust stud alignment if a post sits out of square.
    • Nail top plate (H) and three vertical studs (F) between the right corner posts (A).
Step 4, part by part
Step 4, part by part
Rear and side wall stud framing
Rear and side wall stud framing

Key measurements

  • Rear wall horizontal plate length: 53 in between rear 4x4 posts
  • Side wall top plate length: 65 in (estimated) between front and rear 4x4 posts
  • Wall stud height: 78 in (estimated) between base and top plates
  • Tip: Shift 2x4 stud framing flush on out-of-square corner posts before nailing siding.

Before you move on: Check all three framed walls for plumb with a spirit level before setting the front doorway post.

Step 5: Install the doorway post

Install the 4x4 doorway post, recessed niche framing, and PEX rough-in plumbing.

Watch this step (8:15)

Doorway partition post set in place
Doorway partition post set in place

Parts in this step: (A) Corner post, (B) Doorway partition post, (I) Front partition and niche framing member

You'll need: Shovel, Level, Impact driver, Cordless framing nailer, Tape measure, Pressure-treated posts, 2x4 framing lumber, Exterior structural wood screws, Framing and siding nails, Shower rough-in valve, PEX tubing, PEX fittings and garden hose adapters, Quarter-turn ball valves

  1. 5.1 Set and fasten the 4x4 doorway post
    • Dig a post hole against the 2x6 threshold leaving a 30 in doorway opening.
    • Set and plumb the estimated 96 in doorway partition post (B); fasten with structural screws.
    • Nail six 23 in niche framing members (I) between front corner post (A) and doorway post (B).
    • Mount the shower rough-in valve; crimp 1/2 in PEX lines to the wall head, rain head, and exterior hose bib.
    • Extend rear PEX garden hose stubs past framing so uncoupling hoses does not wet the wood.
Step 5, part by part
Step 5, part by part
Doorway post and niche framing
Doorway post and niche framing
Front doorway and niche framing layout
Front doorway and niche framing layout

Key measurements

  • Doorway width: 30 in between doorway partition post and right corner post
  • Front partition and niche blocking: 23 in between front left corner and doorway posts
  • PEX pipe sizes: 1/2 in for hot and cold shower lines, 3/4 in for untreated well water
  • Tip: Run the third diverter port to an exterior quarter-turn hose bib for outside hot or softened water.
  • Heads up: Wrap exterior PEX stubs in UV-resistant tape or a sleeve against sunlight degradation.

Before you move on: Pressurize PEX lines with garden hoses and leak-check all crimp fittings and valve joints before sheathing.

Step 6: Install the exterior wood siding

Rough-sawn 1x siding wraps the exterior walls and polycarbonate panels cover the 2x4 roof purlins.

Watch this step (10:18)

Rough-sawn siding installed on exterior
Rough-sawn siding installed on exterior

Parts in this step: (A) Corner post, (F) Wall stud, (J) Roof purlin, (K) Rear wall rough-sawn siding board, (L) Side wall exterior rough-sawn siding board, (M) Front partition rough-sawn siding board, (P) Corrugated polycarbonate roof panel

You'll need: Miter saw with stand, Cordless framing nailer, Impact driver, Tape measure, Ladder, Pump sprayer, Rough-sawn 1x lumber, 2x4 framing lumber, Corrugated polycarbonate roof panels, Framing and siding nails, Washered roofing screws, Clear wood preservative

  1. 6.1 Nail rough-sawn 1x boards up the rear exterior plumbing wall
    • Cut rear rough-sawn siding boards (K) to 60 in on the miter saw.
    • Stack courses bottom-up without spacers, butting wavy edges together.
    • Alternate board widths and tones; nail into rear studs (F) and corner posts (A).
  2. 6.2 Sheath the left side and entryway walls with 1x boards
    • Cut and nail estimated 72 in side siding boards (L) up both exterior side walls.
    • Nail 30 in front partition siding boards (M) across the exterior entryway partition.
    • Spray exterior siding and wall cavities with clear wood preservative; dry overnight.
    • Nail seven 60 in roof purlins (J) 16 in on center across the top framing.
    • Fasten three 96 in by 20 in corrugated polycarbonate roof panels (P) to purlins with washered roofing screws.
Step 6, part by part
Step 6, part by part
Exterior siding and polycarbonate roof
Exterior siding and polycarbonate roof

Key measurements

  • Rear siding boards: 60 in across rear exterior wall
  • Side siding boards: 72 in (estimated) across both exterior side walls
  • Front partition siding boards: 30 in across front partition wall
  • Roof purlins: seven 60 in 2x4 purlins spaced 16 in on center
  • Tip: Space 2x4 roof purlins 16 in on center to support heavier metal panels later.

Before you move on: Coat the inside of the exterior siding with wood preservative before enclosing interior walls.

Step 7: Apply wood preservative to the interior walls

Sheathe interior walls, spray clear wood preservative, and fit shower trim and entryway decking.

Watch this step (14:36)

Interior walls coated with wood preservative
Interior walls coated with wood preservative

Parts in this step: (K) Rear wall rough-sawn siding board, (M) Front partition rough-sawn siding board, (N) Interior side wall car siding board, (O) Entryway deck board

You'll need: Miter saw with stand, Circular saw, Cordless framing nailer, Pump sprayer, Impact driver, Rough-sawn 1x lumber, Car siding boards, Clear wood preservative, Shower valve trim kit, Shower heads and shower arm, Composite decking boards, Framing and siding nails

  1. 7.1 Spray clear wood preservative onto the interior siding
    • Nail remaining 60 in boards (K) and 30 in boards (M) to interior plumbing and niche walls.
    • Install estimated 65 in tongue-and-groove car siding boards (N) on both interior side walls.
    • Fill the pump sprayer with clear wood preservative and wet-coat all interior wood.
    • Install the shower valve trim kit, wall shower head, and overhead rain shower head once dry.
    • Rip, notch, and dry-fit five estimated 60 in entryway deck boards (O) on the entryway framing.
Step 7, part by part
Step 7, part by part
Interior siding and entryway decking installed
Interior siding and entryway decking installed

Key measurements

  • Interior car siding boards: 65 in (estimated) along interior side walls
  • Entryway composite deck boards: 60 in (estimated) across entryway floor
  • Wood preservative: 2 gallons total for exterior, cavity, and interior coats
  • Tip: Let the sprayed interior preservative dry before running the wall shower head so water does not wash away the treatment.
  • Heads up: Do not breathe mist; protect skin and eyes while spraying wood preservative inside the stall.

Before you move on: Test all six diverter combinations between wall head, rain head, and exterior hose bib.

Finishing

Floor and Decking

Stain and Sealer

Winterizing Care

Alternatives

These Specs are built from Indy Farm Life's video “Freestanding Wood-Sided Outdoor Shower with Rain Head”. Open the Freestanding Wood-Sided Outdoor Shower with Rain Head project page.